Table of Contents
2.......... Project Information
2.3 Construction
Programme and Activities
2.5 Status
of Environmental Licences, Notification and Permits
3.......... Environmental
Monitoring Requirements
3.1 Construction
Dust Monitoring
3.2 Construction
Noise Monitoring
3.3 Construction
Water Monitoring
4.......... Implementation Status of Environmental
Mitigation Measures
5.......... Monitoring Results
5.1 Construction
Dust Monitoring
5.2 Regular
Construction Noise Monitoring
6.......... ENVIRONMENTAL SITE INSPECTION AND AUDIT
6.2 Summary
of Monitoring Exceedances
6.3 Summary
of Environmental Non-Compliance
6.4 Summary
of Environmental Complaints
6.5 Summary
of Environmental Summon and Successful Prosecutions
7.1 Construction
Programme for the Next Three Month
7.2 Key
Issues for the Coming Month
7.3 Monitoring
Schedule for the Coming Month
8.......... ConclusionS AND RECOMMENDATIONS
List of Tables
Table 2.1.......... Construction Activities
in the reporting month
Table 2.2.......... Contact Information of Key Personnel
Table 2.3.......... Status of Environmental Licenses, Notifications and Permits
Table 3.1 ........ Air Quality Monitoring Equipment
Table 3.2 ........ Location of Construction Dust Monitoring
Station
Table 3.3 ........ Noise Monitoring Parameters, Frequency and
Duration
Table 3.4 ........ Noise Monitoring Equipment for Regular Noise
Monitoring
Table 3.5 ........ Noise Monitoring Stations during
Construction Phase
Table 3.6 ........ Noise Monitoring Parameters, Frequency and
Duration
Table 4.1.......... Status of Required
Submission under Environmental Permit
Table 5.1 ........ Summary of 24-hour TSP Monitoring Result in
the Reporting Period
Table 5.2 ........ Summary of 1-hour TSP Monitoring Result in
the Reporting Period
Table 5.3 ........ Summary of Construction Noise Monitoring
Results in the Reporting Period.
Table 6.1 ........ Observations and Recommendations of Site
Audit
Table 7.1.......... Construction Activities
in the coming three month
List of Figures
Site Layout Plan |
|
Location of Air
Quality Monitoring Station |
|
Locations of Noise
Monitoring Station |
List
of Appendices
Construction
Programme |
|
Project Organization
Structure |
|
Implementation
Schedule of Environmental Mitigation Measures |
|
Summary of Action
and Limit Levels |
|
Calibration
Certificates of Equipment |
|
EM&A Monitoring
Schedules |
|
Air Quality Monitoring
Results and their Graphical Presentations |
|
Noise Monitoring
Results and their Graphical Presentations |
|
Event and Action
Plan |
|
Cumulative
Statistics on Complaints, Notification of Summons and Successful Prosecutions |
|
Monthly Summary
Waste Flow Table |
Central Kowloon Route
– Kai Tak West (CKR-KTW; Contract No. HY/2014/07) (hereafter called “the
Project”) covers part of the construction of the Central Kowloon Route (CKR).
The Project comprises
the follow works:
·
50x30m access shaft with noise enclosure
at Ma Tau Kok (MTK);
·
100m long cut-and-cover (C&C) tunnel
at MTK;
·
Demolition and re-provisioning of MTK
Public Pier;
·
160m long underwater tunnel (UWT) (Stage
1);
·
210m long UWT (Stage 2);
·
60m long C&C tunnel at Kai Tak;
·
130m long depressed road and 200m long
underpass at Kai Tak;
·
390m long underground tunnel ventilation
adit at Kai Tak;
·
Seawall demolition and construction of new
landing steps; and
·
Barging Point enclosure and conveyor
system.
The EM&A programme commenced on 4 April 2018.The impact EM&A for the Project includes air
quality and noise monitoring.
This is the seventh monthly
EM&A Report presenting the EM&A works carried out during the period
between 1 and 31 October 2018. As informed by the Contractor, major activities in
the reporting period were:
Locations |
Site Activities |
Kai Tak |
·
Pipe piling ·
Sheet piling ·
Formation of site access ·
Setup of excavated soil storage area ·
Excavation for ventilation Adit |
Ma Tau Kok |
·
Site clearance ·
Temporary Traffic Management implementation ·
Existing bus shelter relocation ·
Provision of temporary bus shelters ·
Pipe piling works and king post construction |
Kowloon Bay |
·
Seawall Removal ·
Advanced works for pile pile construciton |
Barging Point |
·
Site clearance ·
Barging point construction |
Breaches
of Action and Limit Levels for Air Quality
All 24-hour TSP result was below the Action and Limit Levels at all
monitoring locations in the reporting month.
All 1-hour TSP result was below the Action and Limit Levels at all
monitoring locations in the reporting month.
Breaches
of Action and Limit Levels for Noise
Regular Noise Monitoring
One (1) noise related complaint was received in the reporting month.
Based on the investigation result, the noise nuisance in case was not related
to the project. Therefore, no exceedance of action level of noise was
considered.
No
exceedance of Limit Level of noise was recorded in the reporting month.
Complaint,
Notification of Summons and Successful Prosecution
One (1) complaint (received by Government hotline 1823 on 27 October 2018)
was referred by the Contractor on 31 October 2018, the investigation report was
finalized on 6 November 2018. No notification of summons and successful
prosecution were received in the reporting month.
Reporting
Changes
There was no
reporting change in the reporting month.
Future
Key Issues
Key issues to be
considered in the next three months included:
Locations |
Site Activities |
Kai Tak |
·
Pipe piling ·
Sheet piling ·
Formation of site access ·
Setup of excavated soil storage area ·
Excavation for ventilation adit ·
Watermain diversion ·
Construction of ventilation adit |
Ma Tau Kok |
·
Site clearance ·
Temporary Traffic Management implementation ·
Pipe piling works ·
King post construction ·
Existing drainage diversion works ·
Fresh water pipe installation works |
Kowloon Bay |
·
Seawall Removal ·
Advanced works for pile pile construciton ·
Sheetpile and pipe pile construction for stage 1 temporary
reclamation |
Barging Point |
·
Site Clearance ·
Barging point construction and operation |
·
Section 1: Introduction
·
Section 2: Project Information
·
Section 3: Environmental Monitoring
Requirement
·
Section 4: Implementation Status of
Environmental Mitigation Measures
·
Section 5: Monitoring Results
·
Section 6: Environmental Site Inspection
and Audit
·
Section 7: Environmental
Non-conformance
·
Section 8: Future Key Issues
·
Section 9: Conclusions and Recommendations
(a) construction of approximately 160m long cut-and-cover tunnel and
370m long underwater tunnel between the tunnel section at Ma Tau Kok and the
depressed road of the CKR within Kai Tak Development;
(b) reconstruction of the seawall at Ma Tau Kok public pier, and the
sloping seawall at the Former Kai Tak Airport Runway;
(c) construction of approximately 125m long depressed road and 200m
long underpass of the CKR within Kai Tak Development;
(d) construction of approximately 360m long underground tunnel
ventilation adit of the CKR;
(e) reconstruction of Kowloon City Ferry Pier Public Transport
Interchange; and
(f) other associated works.
Table 2.1 Construction Activities in the reporting month
Locations |
Site Activities |
Kai
Tak |
·
Pipe piling ·
Sheet piling ·
Formation of site access ·
Setup of excavated soil storage area ·
Excavation for ventilation Adit |
Ma
Tau Kok |
·
Site clearance ·
Temporary Traffic Management implementation ·
Existing bus shelter relocation ·
Provision of temporary bus shelters ·
Pipe piling works and king post construction |
Kowloon
Bay |
·
Seawall Removal ·
Advanced works for pile pile construciton |
Barging
Point |
·
Site clearance ·
Barging point construction |
Table 2.2 Contact Information of Key Personnel
Party |
Role |
Position |
Name |
Telephone |
Fax |
Arup-Mott
MacDonald Joint Venture |
Residential
Engineer (ER) |
Engineer’s
Representative |
Mr.
Jeffrey Lau |
2268 3640 |
2268 3954 |
ERM |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker |
Ms. Mandy To |
2271 3313 |
2723 5660 |
Gammon |
Contractor |
Contracts Manager |
Mr. Alan Yan |
2516 8823 |
2516 6260 |
Environmental Manager |
Ms Michelle Tang |
9267 8866 |
2516 6260 |
||
Environmental Officer |
Ms. Phoebe Ng |
9869 1105 |
|||
AECOM |
Contractor’s
Environmental Team (ET) |
ET Leader |
Mr. Y T Tang |
3922 9392 |
2317 7609 |
Table 2.3 Status of Environmental Licenses, Notifications and Permits
Permit / License No. / Notification/
Reference No. |
Valid Period |
Status |
Remarks |
|
From |
To |
|||
Further Environmental
Permit |
||||
FEP-01/457/2013/C |
28 Feb 2018 |
End of Project |
Valid |
-- |
Wastewater
Discharge License |
||||
WT00030290-2018 |
22 Mar 2018 |
31 May 2023 |
Valid |
Ma Tau Kok |
WT00030668-2018 |
27 Apr 2018 |
30 Apr 2023 |
Valid |
Site Office at
Kai Tak West |
WT00030358-2018 |
27 Apr 2018 |
30 Apr 2023 |
Valid |
Kai Tak West |
WT00030333-2018 |
27 Apr 2018 |
30 Apr 2023 |
Valid |
Barging Point
at Portions 4B & 4C |
WT00030330-2018 |
27 Apr 2018 |
30 Apr 2023 |
Valid |
Kowloon Bay |
Construction
Noise Permit |
||||
PP-RE0021-18 |
2 May 2018 |
31 Oct 2018 |
Valid |
Percussive
Piling at Kai Tak Area |
GW-RE0188-18 |
1 Sep 2018 |
28 Feb 2019 |
Valid |
General Works
at Kai Tak Barging Point |
GW-RE0610-18 |
10 Sep 2018 |
9 Nov 2018 |
Valid |
Kai Tak
Pumping Test & General Works |
PP-RE0045-18 |
6 Oct 2018 |
30 Mar 2019 |
Valid |
Percussive
Piling at Kai Tak Area (at grade road and underpass) |
Chemical Waste Producer Registration |
||||
5118-247-G2347-47 |
30 Jan 2018 |
End of Project |
Valid |
-- |
5118-247-G2347-48 |
30 Jan 2018 |
End of Project |
Valid |
-- |
Marine Dumping Permit |
||||
EP/MD/19-043 |
29-Oct-18 |
28-Nov-18 |
Valid |
Permit for T3
sediments disposal trial using T2 sediments |
Billing
Account for Construction Waste Disposal |
||||
7029909 |
22 Jan 2018 |
End of Project |
Account Active |
-- |
Notification
Under Air Pollution Control (Construction Dust) Regulation |
||||
429442 |
5 Jan 2018 |
5 Jul 2025 |
Notified |
-- |
Monitoring Requirements
Monitoring Equipment
Table 3.1 Air Quality Monitoring Equipment
Tisch
Total Suspended Particulate Mass Flow Controlled High Volume Air Sampler |
|
Portable
direct reading dust meter |
Sibata
Digital Dust Monitor |
Monitoring Locations
Table 3.2 Location of Construction Dust Monitoring Station
Location |
Monitoring Station |
Description |
E-A14a
[1] |
Block
B of Merit Industrial Centre |
Rooftop
(13/F) |
[1] The air monitoring station proposed in the
EM&A Manual (i.e. Wyler Gardens with ID: E-A14) was not available for impact
dust monitoring, therefore impact monitoring was conducted at E-A14a as an
alternative which was agreed by the ER, IEC and EPD.
Monitoring
Methodology
(a)
The HVS was
installed in the vicinity of the air sensitive receivers. The following criteria were considered in the
installation of the
HVS as far as practicable:-
(i)
A horizontal platform with
appropriate support to secure the sampler against gusty wind was provided.
(ii)
Two samplers should
not be placed less than 2m apart from each other;
(iii)
The distance between the HVS and
any obstacles, such as buildings, was at least twice the height that the
obstacle protrudes above the HVS.
(iv)
A minimum of 2 meters separation
from walls, parapets and penthouse for rooftop sampler.
(v)
A minimum of 2 meters separation
from any supporting structure, measured horizontally is required.
(vi)
No furnace or incinerator flues
nearby.
(vii)
Airflow around the sampler was
unrestricted.
(viii)
The sampler was located more than
20 meters from any dripline.
(ix)
Any wire fence and gate, required
to protect the sampler, did not obstruct the monitoring process.
(x)
Permission was obtained to set up
the samplers and access to the monitoring station.
(xi)
A secured supply of electricity
was obtained to operate the sampler.
(b)
Preparation of
Filter Papers
(i)
Glass fibre filters, G810 were
labelled and sufficient filters that were clean and without pinholes were
selected.
(ii)
All filters were equilibrated in
the conditioning environment for 24 hours before weighing. The conditioning
environment temperature was around 25 °C and not variable by more than ±3 °C;
the relative humidity (RH) was < 50% and not variable by more than ±5%. A
convenient working RH was 40%.
(iii)
All filter papers were prepared
and analysed by ALS Technichem (HK) Pty
Ltd., which is a HOKLAS accredited laboratory and has
comprehensive quality assurance and quality control programmes.
(c)
Field
Monitoring
(i)
The power supply was checked to ensure the HVS works properly.
(ii)
The filter holder and the area
surrounding the filter were cleaned.
(iii)
The filter holder was removed by
loosening the four bolts and a new filter, with stamped number upward, on a
supporting screen was aligned carefully.
(iv)
The filter was properly aligned
on the screen so that the gasket formed an airtight seal on the outer edges of
the filter.
(v)
The swing bolts were fastened to
hold the filter holder down to the frame.
The pressure applied was sufficient to avoid air leakage at the edges.
(vi)
Then the shelter lid was closed
and was secured with the aluminium strip.
(vii)
The HVS was warmed-up for about 5
minutes to establish run-temperature conditions.
(viii)
A new flow rate record sheet was
set into the flow recorder.
(ix)
On site temperature and
atmospheric pressure readings were taken and the flow rate of the HVS was
checked and adjusted at around 1.3 m3/min, and complied with the
range specified in the EM&A Manual (i.e. 0.6-1.7 m3/min).
(x)
The programmable digital timer
was set for a sampling period of 24 hrs, and the starting time, weather
condition and the filter number were recorded.
(xi)
The initial elapsed time was
recorded.
(xii)
At the end of sampling, on site
temperature and atmospheric pressure readings were taken and the final flow
rate of the HVS was checked and recorded.
(xiii)
The final elapsed time was
recorded.
(xiv)
The sampled filter was removed
carefully and folded in half length so that only surfaces with collected
particulate matter were in contact.
(xv)
It was then placed in a clean
envelope and sealed.
(xvi)
All monitoring information was
recorded on a standard data sheet.
(xvii) Filters were then sent to ALS Technichem
(HK) Pty Ltd. for analysis.
(d)
Maintenance and
Calibration
(i)
The HVS and its accessories were maintained in good working condition, such as
replacing motor brushes routinely and checking electrical wiring to ensure a
continuous power supply.
(ii)
HVSs were calibrated using
TE-5025A Calibration Kit upon installation and thereafter at bi-monthly
intervals.
(iii)
Calibration certificate of the TE-5025A Calibration Kit and the HVSs are provided in Appendix E.
(a)
Measuring Procedures
The measuring procedures of the 1-hour dust
meter are in accordance with the Manufacturer’s Instruction Manual as follows:
(i)
Turn the power on.
(ii)
Close the air collecting opening cover.
(iii)
Push the “TIME SETTING” switch to [BG]
(iv)
Push “START/STOP”
switch to perform background measurement for 6 seconds.
(v)
Turn the knob at SENSI ADJ position to insert
the light scattering plate.
(vi)
Leave the equipment for 1 minute upon “SPAN
CHECK” is indicated in the display.
(vii)
Push “START/STOP” switch to perform automatic
sensitivity adjustment. This measurement takes 1 minute.
(viii)
Pull out the knob and return it to MEASURE
position.
(ix)
Push the “TIME SETTING” switch the time set
in the display to 3 hours.
(x)
Lower down the air collection opening cover.
(xi)
Push “START/STOP” switch to start
measurement.
(b)
Maintenance and Calibration
(i)
The 1-hour TSP meter was
calibrated at 1-year intervals against a continuous particulate TEOM Monitor,
Series 1400ab. Calibration certificates of the Laser Dust Monitors are provided in Appendix E.
Monitoring Schedule for the
Reporting Month
Monitoring Requirements
Table 3.3 Noise Monitoring Parameters, Frequency and Duration
Parameter and Duration |
Frequency |
30-mins
measurement at each monitoring station between 0700 and 1900 on normal
weekdays. Leq, L10 and L90 would be
recorded. |
At least once per week |
Table 3.4 Noise Monitoring Equipment for Regular Noise Monitoring
B&K (Model No. 2238) |
|
Acoustic
Calibrator |
B&K (Model
No. 4231) |
Monitoring Locations
Table 3.5 Noise Monitoring Stations during Construction Phase
Location |
Monitoring Station |
Description |
Measurement |
E-N12a [1] |
19 Hing Yan Street |
Rooftop (9/F) |
Façade |
E-N21a [1] |
Block B of Merit Industrial Centre |
Rooftop (13/F) |
Free field [2] |
Notes:
[1] The noise monitoring stations proposed in the EM&A Manual (i.e.
Grand Waterfront Tower 3 with ID: E-N12 and Hang Chien Court Block J with ID:
E-N21) were not available for impact noise monitoring, therefore impact
monitoring was conducted at E-N12a and E-N21a as an alternative which was
agreed by the ER, IEC and EPD.
[2] A correction of +3 dB(A)
was made to the free field measurements.
Monitoring
Parameters, Frequency and Duration
Table 3.6 Noise Monitoring Parameters, Frequency and Duration
Location |
Parameter and Duration |
Frequency |
E-N12a and E-N21a |
30-mins measurement at each
monitoring station between 0700 and 1900 on normal weekdays. Leq,
L10 and L90 would be recorded. |
At
least once per week |
Monitoring Methodology
(a)
The sound level meter was set on
a tripod at a height of 1.2 m above the ground.
(b)
Façade measurement was made at E-N12a.
(c)
Free field measurements was made
at monitoring location E-N21a. A correction of +3 dB(A) shall be made to the
free field measurements.
(d)
The battery condition was checked to ensure the correct
functioning of the meter.
(e)
Parameters such as frequency
weighting, the time weighting and the measurement time were set as follows:
(i)
frequency weighting: A
(ii)
time weighting: Fast
(iii)
time measurement: Leq(30-minutes)
during non-restricted hours i.e. 0700 – 1900 on normal weekdays.
(f)
Prior to and after each noise
measurement, the meter was calibrated using the acoustic calibrator for 94
dB(A) at 1000 Hz. If the difference in
the calibration level before and after measurement was more than 1 dB(A), the
measurement would be considered invalid and repeat of noise measurement would
be required after re-calibration or repair of the equipment.
(g)
During the monitoring period, the
Leq, L10 and L90 were recorded. In addition, site conditions and noise
sources were recorded on a standard record sheet.
(h)
Noise measurement was paused
during periods of high intrusive noise (e.g. dog barking, helicopter noise) if
possible. Observations were recorded when intrusive noise was unavoidable.
(i)
Noise monitoring was cancelled in
the presence of fog, rain, wind with a steady speed exceeding 5m/s, or wind
with gusts exceeding 10m/s.
(a)
The microphone
head of the sound level meter was cleaned with soft cloth at
regular intervals.
(b)
The meter and
calibrator were sent to the supplier or HOKLAS laboratory to check and
calibrate at yearly intervals.
(c)
Calibration
certificates of the sound level meters and acoustic calibrators are provided
in Appendix E.
Monitoring Schedule for the Reporting
Month
Table 4.1 Status of Required Submission under Environmental Permit
EP Condition |
Submission |
Submission
Date |
Condition 3.4 of |
Monthly EM&A Report for September 2018 |
13 October 2018 |
Condition 3.3 of |
Water Quality Baseline Monitoring Report |
10 October 2018 |
Table 5.1 Summary of 24-hour
TSP Monitoring Result in the Reporting Period (To
be updated)
ID |
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
E-A14a |
58.8 |
21.1 – 93.2 |
197.3 |
260 |
Table 5.2 Summary of 1-hour TSP Monitoring Result in the Reporting Period
ID |
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
E-A14a |
68.2 |
59.6 – 73.1 |
302.4 |
500 |
Table 5.3 Summary of Construction Noise Monitoring Results in the Reporting Period
ID |
Range, dB(A), Leq (30
mins) |
Limit Level, dB(A), Leq
(30 mins) |
E-N12a |
58.1
– 64.7 |
75 |
E-N21a |
60.1
– 65.9 |
75 |
Table 6.1 Observations and Recommendations of Site Audit
Parameters |
Date |
Observations and Recommendations |
Follow-up |
Air Quality |
03 October 2018 |
· Haul
road was observed in dry condition at Kai Tak. The Contractor was reminded to
provide water spraying regularly on the haul road. |
The
item was rectified by the Contractor on 04 October 2018. |
11 October 2018 |
Reminder: · The
Contractor was reminded to replace the damaged NRMM label of the generator at
Kai Tak. |
The
item was rectified by the Contractor on 15 October 2018. |
|
24 October 2018 |
· Haul
roads were observed to be dry at Kai Tak. The Contractor was reminded to
provide water spraying regularly to prevent dust generation. |
The
item was rectified by the Contractor on 30 October 2018. |
|
31 October 2018 |
Reminder: · The
Contractor was reminded to provide proper cover for the stockpile to minimize
the active area of stockpile at Kai Tak. |
The
item will be follow up in next site inspection. |
|
Noise |
Nil |
Nil |
Nil |
Water Quality |
03 October 2018 |
Reminder: · The
Contractor was reminded to place the sand bags or proper protection for the
gully to prevent any contaminated surface runoff from site at Ma Tau Kok. |
The
item was rectified by the Contractor on 05 October 2018. |
11 October 2018 |
· Few
of the existing gully were observed without protective measure. The
Contractor was reminded to provide the protective measure for prevention of
site surface runoff at Ma Tau Kok. |
The
item was rectified by the Contractor on 13 October 2018. |
|
26 September 2018 |
Reminder: · The
Contractor was reminded to place the sand bags or proper protection for the
gully to prevent any contaminated surface runoff from site at Ma Tau Kok. |
The
item was rectified by the Contractor on 02 October 2018. |
|
Waste/ Chemical Management |
03 October 2018 |
· Accumulated
waste was observed at Ma Tau Kok. The Contractor was reminded to remove the
waste regularly |
The
item was rectified by the Contractor on 08 October 2018. |
26 September 2018 |
· Chemical
waste containers were observed without proper labelling at chemical waste
storage container of Ma Tau Kok. The Contractor was reminded to fit proper
label for chemical waste containers. |
The
item was rectified by the Contractor on 02 October 2018. |
|
Landscape & Visual |
Nil |
Nil |
Nil |
Permits/ Licenses |
16 October 2018 |
· Valid
environmental permit was not observed at the vehicle site entrances of Ma Tau
Kok. The Contractor was reminded to display the valid environmental permit at
vehicle site entrance. |
The item was rectified by the Contractor on 17 October 2018. |
Table 7.1 Construction Activities in the coming three month
Locations |
Site Activities |
Kai
Tak |
·
Pipe piling ·
Sheet piling ·
Formation of site access ·
Setup of excavated soil storage area ·
Excavation for ventilation adit ·
Watermain diversion ·
Construction of ventilation adit |
Ma
Tau Kok |
·
Site clearance ·
Temporary Traffic Management implementation ·
Pipe piling works ·
King post construction ·
Existing drainage diversion works ·
Fresh water pipe installation works |
Kowloon
Bay |
·
Seawall Removal ·
Advanced works for pile pile construciton ·
Sheetpile and pipe pile construction for stage 1 temporary
reclamation |
Barging
Point |
·
Site Clearance ·
Barging point construction and operation |